Announcements 2026

Voluntary production update

Northam is pleased to report solid performance from each of our operations for the financial year ended 30 June 2026 (“F2026”), while project development continues apace.


Northam is pleased to report solid performance from each of our operations for the financial year ended 30 June 2026 (“F2026”), while project development continues apace.

The following key production metrics exceeded guidance:

  • Record total equivalent refined metal produced from own operations of 938 754 oz 4E
  • Record equivalent refined metal purchased from third parties of 158 138 oz 4E
  • Record total chrome concentrate produced and sold of 1 690 495 tonnes
  • Record total 4E metal sold of 1 087 327 oz

All other production metrics were within guidance.

All operations have performed well. Zondereinde continues to benefit from focussed Merensky stoping in the Western extension, together with logistical decongestion resulting from the shift of UG2 stoping to the higher-yielding eastern portions of the mine. Booysendal’s production exceeds steady state and is continuing to focus on incremental sustainable productivity gains, while Eland continues to ramp-up on schedule.

Strong production growth was recorded at Eland, with marginal improvements at Zondereinde ahead of the commissioning of 3 shaft, and at Booysendal on the back of further productivity gains. This once again demonstrates the quality of these operations.

Mining tonnages and grades across the group are expected to improve further over the coming two years as our growth and innovation projects reach completion and deliver on their planned objectives. This, together with an expected increase in mineable reserves, will provide important additional operational flexibility.

Key Platinum Group Metals (“PGMs”) production metrics for F2026 compared to the financial year ended 30 June 2025 (“F2025”) are as follows:

Performance relative to guidance F2026 F2025 % variance

 

 

oz 4E

oz 4E

 

Equivalent refined metal produced from own operations at Zondereinde

Within

333 050

330 769

0.7 

Metal in concentrate produced from own operations at Booysendal

Exceeded

531 668

512 147

3.8 

Metal in concentrate produced from own operations and surface sources at Eland

Within

91 205

72 442

25.9 

Total equivalent refined metal produced from own operations

Exceeded

938 754

899 244

4.4 

Equivalent refined metal purchased from third parties

Exceeded

158 138

127 171

24.4 

Total equivalent refined metal produced from own operations including refined metal purchased from third parties

Exceeded

1 096 892

1 026 415

6.9 

Total refined metal produced

*

1 032 509

937 942

10.1 

Refined metal sold

*

1 026 346

933 210

10.0 

Concentrate and recycled material sold disclosed as equivalent ounces

*

60 981

73 265

(16.8)

Total metal sold

Exceeded

1 087 327

1 006 475

8.0 

* Not guided

 

Group production of chrome concentrate increased by 17.4% to 1 690 495 tonnes (F2025: 1 439 752 tonnes), due to improved UG2 tonnage throughput, feed grades and concentrator yields, particularly at Eland, where yields have more than doubled during the past year.

 

Performance relative to guidance F2026 F2025 % variance

 

 

tonnes

tonnes

 

Chrome concentrate produced at Zondereinde

*

507 900

497 438

2.1 

Chrome concentrate produced at Booysendal

*

873 764

735 706

18.8 

Chrome concentrate produced at Eland

*

308 831

206 608

49.5 

Total chrome concentrate produced

Exceeded

1 690 495

1 439 752

17.4 

Zondereinde

Solid production performance, together with the commissioning of 3 shaft, was marred by the tragic passing of three of our employees in separate and unrelated incidents.

Mr. Aubrey Botswe, a locomotive guard, was struck by a locomotive. Mr. Luyanda Kunyalele, a rock drill operator, was struck by a fall of ground. Mr. Ofentse Modiselle, an artisan assistant, fell from an overhead crane at the metallurgical facility, the cause of which is still being investigated.

We remain acutely aware of the potential severity of injuries which may result from safety incidents and are proactively working to minimise both potential incidents and consequential injuries.

Both Merensky and UG2 mined tonnages increased compared to the previous year as a result of the establishment of new stoping areas for Merensky in the Western extension, and UG2 on the eastern side of the mine. Merensky mill feed grades from the Western extension have been depressed for the past four years as a result of necessary under-stoping of 3 shaft, accelerated development and excessive backfill dilution due to the distance from the main shafts. These are matters that will be progressively resolved following the commissioning of 3 shaft. UG2 grades present in the eastern side of the mine will continue to be above historical levels. We expect improvement in combined concentrator feed grades, closer to historical levels, over the coming 18 months.

Higher feed tonnages achieved, although somewhat offset by marginally lower 4E concentrator feed grades, resulted in equivalent refined metal from own operations improving to 333 050 oz 4E (F2025: 330 769 oz 4E).

Booysendal

Continued focus on safety, together with a strong production performance, were key features of the year.

The mine surpassed 12.7 million fatality free shifts during June 2026, and, more importantly, remains fatality free since inception over 15 years ago.

Production of metal in concentrate from own operations increased by 3.8% to 531 668 oz 4E (F2025: 512 147 oz 4E), exceeding planned steady state levels. All currently operating mining modules are contributing.

The expansion of the South tailings storage facility (“TSF”) which commenced at the end of the first half of the financial year is expected to be completed in 12 months’ time. This will enable further production growth.

Eland

Key production metrics relating to Eland for F2026 compared to F2025 are as follows:

F2026 F2025 % variance

Square metres mined

169 243

108 917

55.4 

Development metres

13 388

12 519

6.9 

Surface sources including TSF tonnes

114 455

922 481

(87.6)

Toll treated UG2 ore tonnes from Zondereinde

107 663

58 629

83.6 

Tonnes mined

1 290 647

1 082 955

19.2 

Tonnes hoisted

1 276 491

1 007 134

26.7 

Run of Mine tonnes milled

1 388 310

1 074 940

29.2 

Surface sources tonnes milled

114 455

922 481

(87.6)

Total tonnes milled

1 502 765

1 997 421

(24.8)

Head grade (4E g/t)

2.74

2.09

31.1 

Head grade (6E g/t)

3.49

2.71

28.8 

PGM concentrate recoveries (%)

73.0

60.2

21.3 

Stockpile tonnes

62 524

258 680

(75.8)

4E metal in concentrate produced from own operations and surface sources

91 205

72 442

25.9 

Chrome concentrate produced tonnes

308 831

206 608

49.5 

The ramp-up of Eland continues, as mineable reserves grow and stoping crew build-up continues, and the reconfiguration of the mine’s ventilation circuit enables multi-blast conditions. These conditions contribute to accelerated decline development rates, whilst de-risking the mine build programme.

Batch treatment of Run of Mine ore is ongoing, together with treatment of third-party surface material. The ramp-up of underground stoping is improving feed volumes and grades to the concentrator, and ongoing enhancements to the concentrator circuits are improving recovery of both PGMs and chrome.

Underground ore production improved by 55.4% as a result of the number of operational stoping crews increasing to 50. However, a temporary suspension of tailings retreatment reduced total milled tonnage by 24.8%. This was offset by a 31.1% improvement in mill feed grade, and a 21.3% improvement in PGM concentrate recovery, which led to a 25.9% increase in own production to 91 205 oz 4E (F2025: 72 442 oz 4E).

In addition, spare capacity in the PGM and chrome circuits allows for the treatment of UG2 ore from Zondereinde, where mining production currently exceeds concentrator capacity. This benefits both operations and processing of Zondereinde UG2 ore at Eland commenced during the second half of F2026.

Looking forward

Northam’s growth strategy is rooted in our belief in the inherent and long-term, sustainable value of the metals we produce, together with our long-held view of shrinking global primary supply.

This strategy has required significant capital investments, both in the acquisition of quality assets, together with the development of those assets into world class mining and mineral processing operations.

Northam’s view remains that primary supply will continue to decline unabated well into the next decade, due to the extended lead times for developing new mines, exacerbated by periodic fluctuations in PGM basket pricing.

Northam’s operations are high-yielding, quality assets with long operating lives, and our relative market share of primary PGM and chrome production is expected to continue to increase over time.

This voluntary production update has not been reviewed and reported on by the group’s external auditors.

Johannesburg
13 July 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Disclosure of an acquisition of a beneficial interest in Northam Holdings securities

In accordance with section 122(3)(b) of the Companies Act, No. 71 of 2008, as amended (“Companies Act”), and paragraph 6.54 of the JSE Listings Requirements, Northam Holdings shareholders are advised that the company has received notification, in the prescribed form, from BlackRock, Inc. (“BlackRock”), advising that it has acquired a beneficial interest in the securities of Northam Holdings, such that BlackRock now holds a beneficial interest of 5.02% in the company’s total issued share capital.


In accordance with section 122(3)(b) of the Companies Act, No. 71 of 2008, as amended (“Companies Act”), and paragraph 6.54 of the JSE Listings Requirements, Northam Holdings shareholders are advised that the company has received notification, in the prescribed form, from BlackRock, Inc. (“BlackRock”), advising that it has acquired a beneficial interest in the securities of Northam Holdings, such that BlackRock now holds a beneficial interest of 5.02% in the company’s total issued share capital.

The company will file the relevant notification with the Takeover Regulation Panel and the Companies and Intellectual Property Commission, as required in terms of sections 122(3)(a) and 122(3A) of the Companies Act.

The board of directors of Northam Holdings (“Board”) accepts responsibility for the information contained in this announcement and certifies that, to the best of the Board’s knowledge and belief, the information contained in this announcement is true and that there are no facts that have been omitted which would make any statement in this announcement false or misleading and that this announcement contains all information required by law and the JSE Listings Requirements.

Johannesburg
7 July 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Interest payment notification – NHM022

Northam bondholders are advised of the following interest payment due on Tuesday, 23 June 2026


Northam bondholders are advised of the following interest payment due on Tuesday, 23 June 2026:

Bond Code: NHM022
ISIN: ZAG000190133
Coupon: 10.500%
Interest Period: 23 March 2026 to 22 June 2026
Interest Amount Due: R92 630 136.99
Payment Date: 23 June 2026
Date Convention: Following Business Day

Johannesburg
18 June 2026

Debt Sponsor
One Capital

Read more

Interest payment notifications – NHM027, NHM028 and NHM029

Northam bondholders are advised of the following interest payments due on Monday, 15 June 2026:


Northam bondholders are advised of the following interest payments due on Monday, 15 June 2026:

Bond Code: NHM027
ISIN: ZAG000216052
Coupon: 8.850%
Interest Period: 13 March 2026 to 14 June 2026
Interest Amount Due: R58 324 167.12
Payment Date: 15 June 2026
Date Convention: Following Business Day
Bond Code: NHM028
ISIN: ZAG000216045
Coupon: 9.250%
Interest Period: 13 March 2026 to 14 June 2026
Interest Amount Due: R14 960 164.38
Payment Date: 15 June 2026
Date Convention: Following Business Day
Bond Code: NHM029
ISIN: ZAG000216037
Coupon: 9.650%
Interest Period: 13 March 2026 to 14 June 2026
Interest Amount Due: R62 453 213.70
Payment Date: 15 June 2026
Date Convention: Following Business Day

Johannesburg
10 June 2026

Debt Sponsor
One Capital

Read more

Interest payment notifications – NHM021, NHM025 and NHM026 and capital settlement of NHM025

Northam bondholders are advised of the following interest payments due on Monday, 25 May 2026 and Tuesday, 26 May 2026:


Northam bondholders are advised of the following interest payments due on Monday, 25 May 2026 and Tuesday, 26 May 2026:

Bond Code: NHM021
ISIN: ZAG000181496
Coupon: 10.883%
Interest Period: 26 February 2026 to 25 May 2026
Interest Amount Due: R15 205 489.07
Payment Date: 26 May 2026
Date Convention: Following Business Day
Bond Code: NHM025
ISIN: ZAG000195934
Coupon: 9.633%
Interest Period: 25 February 2026 to 24 May 2026
Interest Amount Due: R21 139 816.44
Payment Date: 25 May 2026
Date Convention: Following Business Day
Bond Code: NHM026
ISIN: ZAG000195942
Coupon: 10.383%
Interest Period: 25 February 2026 to 24 May 2026
Interest Amount Due: R32 659 513.15
Payment Date: 25 May 2026
Date Convention: Following Business Day

Capital settlement notification

Northam bondholders are further advised that NHM025 will be settled in full on its Maturity Date, being Monday, 25 May 2026. Following the settlement of NHM025 amounting to R900.0 million, the capital outstanding under Northam’s R15.0 billion Domestic Medium Term Note Programme will amount to R11 063.0 million.

Johannesburg
20 May 2026

Debt Sponsor
One Capital

Read more

Interest Payment Notification – NHM022

Northam bondholders are advised of the following interest payment due on Monday, 23 March 2026:


Northam bondholders are advised of the following interest payment due on Monday, 23 March 2026:

Bond Code: NHM022
ISIN: ZAG000190133
Coupon: 10.525%
Interest Period: 23 December 2025 to 22 March 2026
Interest Amount Due: R90 832 191.78
Payment Date: 23 March 2026
Date Convention: Following Business Day

Johannesburg
18 March 2026

Debt Sponsor
One Capital

Read more

Dealings in securities

In compliance with paragraphs 6.77 to 6.89 of the JSE Listings Requirements, Northam shareholders are advised of the following dealings in Northam Holdings ordinary shares (“Shares”) by an associate of Mr Wouter André Hanekom, an independent non-executive director of the company:


In compliance with paragraphs 6.77 to 6.89 of the JSE Listings Requirements, Northam shareholders are advised of the following dealings in Northam Holdings ordinary shares (“Shares”) by an associate of Mr Wouter André Hanekom, an independent non-executive director of the company:

Name of associate: Any New Investments Proprietary Limited (“Any New Investments”)
Relationship with director: Mr Hanekom is a director of Any New Investments and a beneficiary and trustee of the sole shareholder of Any New Investments, The André Hanekom Family Trust
Nature of the transactions: Purchase of Shares
Date of the transactions: 11 March 2026
Total number of Shares: 5 100
Price per Share Various trades with the following price information:
  • ­ volume weighted average price of R391.2684
  • ­ highest price of R391.30
  • ­ lowest price of R390.69
Total value of transactions: R1 995 468.96

The transactions were effected on-market and the nature and extent of Mr Hanekom’s interest in the Shares is indirect beneficial. Clearance to deal was obtained in terms of paragraph 6.83 of the JSE Listings Requirements.

Johannesburg
12 March 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Interest payment notifications – NHM027, NHM028 and NHM029

Northam bondholders are advised of the following interest payments due on Friday, 13 March 2026:


Northam bondholders are advised of the following interest payments due on Friday, 13 March 2026:

Bond Code: NHM027
ISIN: ZAG000216052
Coupon: 8.925%
Interest Period: 15 December 2025 to 12 March 2026
Interest Amount Due: R55 064 071.23
Payment Date: 13 March 2026
Date Convention: Following Business Day
Bond Code: NHM028
ISIN: ZAG000216045
Coupon: 9.325%
Interest Period: 15 December 2025 to 12 March 2026
Interest Amount Due: R14 118 816.44
Payment Date: 13 March 2026
Date Convention: Following Business Day
Bond Code: NHM029
ISIN: ZAG000216037
Coupon: 9.725%
Interest Period: 15 December 2025 to 12 March 2026
Interest Amount Due: R58 921 243.84
Payment Date: 13 March 2026
Date Convention: Following Business Day

Johannesburg
10 March 2026

Debt Sponsor
One Capital

Read more

Condensed reviewed interim financial results for the six months ended 31 December 2025 and a record interim cash dividend declaration

Shareholders of Northam Holdings (“Shareholders”) are hereby advised that the company has today published its condensed reviewed interim financial results for the six months ended 31 December 2025 (“Interim Results”).


Shareholders of Northam Holdings (“Shareholders”) are hereby advised that the company has today published its condensed reviewed interim financial results for the six months ended 31 December 2025 (“Interim Results”).

Financial results overview

    Six months ended 31 December 2025 Six months ended 31 December 2024 Variance
Sales revenue R000 23 250 372 14 534 271 60.0%
Operating profit R000 5 840 257 1 083 226 439.2%
Operating profit margin % 25.1 7.5 234.7%
Basic earnings per share cents 2 006.0 61.5 >1 000.0%
Headline earnings per share cents 1 524.0 61.1 >1 000.0%
Dividends per share cents 700.0 15.0 >1 000.0%
EBITDA* R000 7 451 127 1 761 810 322.9%
EBITDA margin % 32.0 12.1 164.5%

* Earnings before interest, taxation, depreciation, amortisation and reversal of impairment.

Record interim cash dividend declaration

For the six months ended 31 December 2025, the board of directors of the company (“the board”) has resolved to declare and pay a record interim gross cash dividend of 700.0 cents per share (31 December 2024: 15.0 cents per share and for 30 June 2025: 200.0 cents per share), which in aggregate amounts to a gross cash dividend of approximately R2.8 billion. The interim gross cash dividend has been declared from income reserves.

A dividend withholding tax of 20.0% will be applicable to Shareholders who are not exempt from, or who do not qualify for, a reduced rate of dividend withholding tax. Accordingly, for those Shareholders subject to dividend withholding tax at a rate of 20.0%, the interim net cash dividend will amount to 560.0 cents per share (31 December 2024: 12.0 cents per share and for 30 June 2025: 160.0 cents per share).

The following dates are applicable to the interim cash dividend:

Last day to trade to qualify and participate in the dividend (cum dividend), on Tuesday, 17 March 2026
Trading ex-dividend, on Wednesday, 18 March 2026
Record date to determine which Shareholders are eligible to receive the dividend, on Friday, 20 March 2026
Payment date of the dividend, on Monday, 23 March 2026

Shareholders may not dematerialise or rematerialise their shares between Wednesday, 18 March 2026 and Friday, 20 March 2026, both days inclusive.

The following additional information is disclosed regarding the interim cash dividend:

  • Northam Holdings’ issued share capital as at the declaration date is 400 102 916 ordinary shares (of which 1 share is held by Northam Platinum, a subsidiary of Northam Holdings)
  • Northam Holdings’ registration number is 2020/905346/06
  • Northam Holdings’ income tax reference number is 9586451198

About this announcement

This announcement, which contains information extracted from the Interim Results, is the responsibility of the board and has been prepared in compliance with the JSE Listings Requirements.

As the information in this announcement does not provide all of the details, any investment decisions should be based on the published condensed reviewed interim financial results for the six months ended 31 December 2025 (which incorporates the external auditor’s report in which PricewaterhouseCoopers Incorporated expressed an unmodified review conclusion) accessible via the JSE cloudlink at: https://senspdf.jse.co.za/documents/2026/JSE/ISSE/NPHE/Interim_26.pdf and on the company’s website at: https://northam.co.za/component/jdownloads/?task=download.send&id=1621&catid=187&m=0&Itemid=347.

Johannesburg
27 February 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Interest payment notifications – NHM021, NHM025 AND NHM026

Northam bondholders are advised of the following interest payments due on Wednesday, 25 February 2026 and Thursday, 26 February 2026::


Northam bondholders are advised of the following interest payments due on Wednesday, 25 February 2026 and Thursday, 26 February 2026::

Bond Code: NHM021
ISIN: ZAG000181496
Coupon: 11.033%
Interest Period: 26 November 2025 to 25 February 2026
Interest Amount Due: R15 934 674.74
Payment Date: 26 February 2026
Date Convention: Following Business Day
Bond Code: NHM025
ISIN: ZAG000195934
Coupon: 9.783%
Interest Period: 25 November 2025 to 24 February 2026
Interest Amount Due: R22 192 668.49
Payment Date: 25 February 2026
Date Convention: Following Business Day
Bond Code: NHM026
ISIN: ZAG000195942
Coupon: 10.533%
Interest Period: 25 November 2025 to 24 February 2026
Interest Amount Due: R34 248 121.64
Payment Date: 25 February 2026
Date Convention: Following Business Day

Johannesburg
20 February 2026

Debt Sponsor
One Capital

Read more

R2.0 billion increase to the Revolving Credit Facility (“RCF”)

Northam is pleased to announce that it has successfully concluded and implemented an agreement to increase its existing RCF, from R11.3 billion to R13.3 billion (“RCF Increase”). The RCF matures in August 2027 and this date as well as the remaining material terms and conditions pertaining to the RCF remain unchanged.


Northam is pleased to announce that it has successfully concluded and implemented an agreement to increase its existing RCF, from R11.3 billion to R13.3 billion (“RCF Increase”). The RCF matures in August 2027 and this date as well as the remaining material terms and conditions pertaining to the RCF remain unchanged.

Northam’s total available banking facilities now amount to R14.3 billion, comprising the increased RCF of R13.3 billion and existing general banking facilities of R1.0 billion.

Northam is a large and growing energy user, and in order to improve both security and diversity of energy supply, whilst simultaneously reducing long-term energy costs and our impact on the environment, we have been actively and aggressively pursuing an alternative and renewable energy programme.

To date the company has entered into various power purchase agreements with independent power producers in respect of new renewable energy projects, the construction of which are well advanced and, already in some instances, producing renewable energy. In addition, we are developing various own-build and owned renewable energy projects at our mine sites, comprising photovoltaic solar plants supplemented with utility scale battery storage.

The RCF Increase allows Northam to accelerate construction of these various own-build projects.

Northam’s alternative energy program is scheduled to provide more than 70% of our total energy requirement from renewable sources before the end of the current decade, with a concomitant significant reduction in Northam’s carbon emissions and increase in energy availability factor on a competitive cost basis.

Alet Coetzee, Northam’s Chief Financial Officer, said “The RCF Increase provides Northam with the necessary flexibility and additional capacity to accelerate our efforts to enhance the security of our energy supply through the use of renewable sources, and to also significantly decrease our contribution towards Greenhouse Gas emissions, without affecting our other capital programmes or our ability to return value to shareholders whilst doing so.”

Johannesburg
20 February 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Trading statement and trading update for the six-month period ended 31 December 2025

In terms of paragraph 3.4(b) of the JSE Limited Listings Requirements, companies are required to publish a trading statement as soon as they are satisfied, with a reasonable degree of certainty, that the financial results for the current reporting period will differ by at least 20% from the financial results of the previous corresponding period.


Key metrics

  • Total equivalent refined platinum group metal (“PGM”) produced from own operations increased by 3.7% to 467 818 oz 4E (H1 F2025: 451 213 oz 4E).
  • Production of chrome concentrate increased by 14.8% to 822 759 tonnes (H1 F2025: 716 622 tonnes), on the back of improvements in UG2 tonnage throughput, feed grades and concentrator yields.
  • Total metal sold increased by 13.7% to 519 192 oz 4E (H1 F2025: 456 544 oz 4E).
  • Sales revenue rose by 60.0% to R23.3 billion (H1 F2025: R14.5 billion), attributable to a 53.1% appreciation in the Rand 4E basket price, together with increased metal sold.
  • Group unit cash cost per equivalent refined 4E ounce increased by 7.2% to R27 208/4E oz (H1 F2025: R25 381/4E oz), as cost control and production growth tempered ongoing mining cost inflation.
  • Operating profit grew by 439.2% to R5.8 billion (H1 F2025: R1.1 billion), as a result of higher sales volumes and improved metal prices.
  • Basic earnings per share is expected to increase to between 2 000.5 cents and 2 011.5 cents (H1 F2025: 61.5 cents).
  • Headline earnings per share is expected to increase to between 1 518.5 cents and 1 529.5 cents (H1 F2025: 61.1 cents).
  • Net debt of R2.6 billion measured against a 12-month rolling EBITDA of R10.6 billion results in a net debt to EBITDA ratio of 0.24.
  • Available banking facilities of R12.3 billion remain fully undrawn at period end.

Introduction

In terms of paragraph 3.4(b) of the JSE Limited Listings Requirements, companies are required to publish a trading statement as soon as they are satisfied, with a reasonable degree of certainty, that the financial results for the current reporting period will differ by at least 20% from the financial results of the previous corresponding period.

Northam Holdings’ financial results for the six-month period ended 31 December 2025 (“H1 F2026” or the “period”) are underpinned by a solid production performance. Northam Holdings expects to report an increase in basic and headline earnings per share for H1 F2026 compared to the previous six-months ended 31 December 2024 (“H1 F2025”).

The table below provides key earnings per share information for H1 F2026, compared to that of H1 F2025:

H1 F2026 H1 F2025 % variance
Basic earnings per share (cents) 2 000.5 – 2 011.5 61.5 >1 000.0
Headline earnings per share (cents) 1 518.5 – 1 529.5 61.1 >1 000.0
Number of shares in issue including treasury shares 400 102 916 396 238 229 1.0
Weighted average number of shares in issue# 393 724 561 389 859 874 1.0

#The weighted average number of shares in issue has been used to determine the basic earnings per share and headline earnings per share.

Safety

All operations remained fatality free throughout the period, achieving notable safety milestones.

Booysendal surpassed 12 million fatality free shifts during December 2025, and remains fatality free since inception. Zondereinde recorded 2 million fatality free shifts during October 2025 and Eland recorded 1 million fatality free shifts in December 2025.

The group’s lost time injury incidence rate (LTIIR), expressed per 200 000 hours worked, equalled 0.55 (F2025: 0.61).

The safety of our employees remains of utmost importance and takes precedence over any production, operational or financial objectives. Improving safety performance, as well as the health and wellness of our workforce, remain critical focus areas for the business.

Production

Key production metrics are as follows:

H1 F2026 H1 F2025
PGM production oz 4E oz 4E % variance
Equivalent refined metal production from own operations at Zondereinde 170 262 165 076 3.1
Concentrate production from own operations at Booysendal 261 148 256 759 1.7
Concentrate production from own operations at Eland 44 842 37 488 19.6
Total equivalent refined metal production from own operations 467 818 451 213 3.7

Equivalent refined PGMs purchased from third parties totalled 83 448 oz 4E (H1 F2025: 59 743 oz 4E), representing an increase of 39.7%.

All of our operations performed well and recorded improved metal production.

Zondereinde continues to benefit from logistics decongestion as a result of the ongoing shift of UG2 stoping from the western to the higher-yielding eastern portions of the mine, as well as an increase in mining productivity arising from focussed Merensky stoping in the Western extension.

Booysendal continues to focus on productivity and efficiency gains.

Eland is making steady progress in its ramp-up, with both square metres and tonnes mined in line with expectations.

At Zondereinde, the ramp-up of stoping continues within the Western extension section reflecting an improvement in Merensky tonnes mined. Equipping of 3 shaft for personnel and material transport, as well as the provision of services, is nearing completion. Reaming of 3a ventilation shaft also continues. Both shafts are scheduled for commissioning in April 2026. This will deliver sustainable efficiency benefits to mining in the Western extension. Pilot drilling of 4 shaft, which will be a rock hoisting shaft, is complete, and reaming has commenced.

At Booysendal, decline development is continuing in order to increase mineable reserves and enhance operational flexibility.

At Eland, the ramp-up of ore production from underground mining continues. In addition, the reconfiguration of the mine’s ventilation circuit has enabled multi-blast conditions, which is allowing accelerated decline development rates, further de-risking the mine build programme. Focus remains on strike and raise development in order to grow mineable reserves. Stoping ramp-up is improving feed volumes and grades to the concentrator, and further enhancements to the concentrator circuits are yielding additional benefits to PGM and chrome production.

At the group’s metallurgical facilities, upgrades to the Base Metal Removal (“BMR”) plant are almost complete and the furnace slag concentrator is processing slag inventory at a satisfactory pace.

Group production of chrome concentrate increased by 14.8% to 822 759 tonnes (H1 F2025: 716 622 tonnes), on the back of improvements in UG2 tonnage throughput, feed grades and concentrator yields. Eland now contributes more than 20% of group chrome concentrate production.

H1 F2026 H1 F2025
Chrome concentrate production tonnes tonnes % variance
Production at Zondereinde 241 454 242 402 (0.4)
Production at Booysendal 414 289 358 833 15.5
Production at Eland 167 016 115 387 44.7
Total group production 822 759 716 622 14.8

Unit cash costs

The unit cash cost for the group amounted to R27 208/4E oz (H1 F2025: R25 381/4E oz), representing an increase of 7.2% for the period. Unit cash costs increased at Zondereinde by 5.5% to R28 210/4E oz, at Booysendal by 2.8% to R18 897/4E oz, and at Eland by 18.8% to R42 441/4E oz. Disciplined cost control and efficiency gains at Zondereinde and Booysendal moderated normal mining inflation, while cost inflation at Eland is driven by the crew build-up and an overall increase in the number of employees.

Unit cash costs per 4E ounce for the group, and per operation, are as follows:

H1 F2026 H1 F2025
R/4E oz R/4E oz % variance
Zondereinde cash cost per equivalent refined 4E ounce 28 210 26 752 (5.5)
Booysendal cash cost per 4E ounce in concentrate produced 18 897 18 383 (2.8)
Eland cash cost per 4E ounce in concentrate produced 42 441 35 711 (18.8)
Group cash cost per equivalent refined 4E ounce 27 208 25 381 (7.2)

Sales revenue

Sales revenue rose by 60.0% to R23.3 billion (H1 F2025: R14.5 billion). The increase is primarily attributable to a 53.1% increase in the Rand 4E basket price achieved, together with a 13.7% increase in metal sold.

As a result, total revenue per equivalent refined 4E ounce sold increased by 40.7% to R44 782/4E oz (H1 F2025: R31 835/4E oz).

The table below summarises metal volumes dispatched to the group’s precious metal refiners, compared to metal volumes refined and sold, together with the average USD sales prices achieved (expressed per metal and on a 4E basis) during the period:

Dispatched Total refined metal produced Total equivalent refined metal sold (including the sale of concentrate) Average sales prices achieved
oz oz oz USD/oz
Platinum 310 117 294 764 311 385 1 546
Palladium 148 189 142 093 150 685 1 330
Rhodium 47 860 49 280 52 119 7 284
Gold 4 818 4 709 5 003 3 843
Total 4E 510 984 490 846 519 192 2 081

Included in total equivalent refined metal sold is concentrate sold to a third party to honour legacy offtake agreements relating to the Everest and Maroelabult operations, which contained 32 237 oz 4E in concentrate (H1 F2025: 37 341 oz 4E).

Financial results

Sales revenue increased by 60.0%, compared to an increase in cost of sales of 29.4%. This resulted in an operating profit of R5.8 billion (H1 F2025: R1.1 billion), and an operating profit margin of 25.1% (H1 F2025: 7.5%).

Earnings before interest, taxation, depreciation and amortisation (“EBITDA”) amounted to R7.5 billion (H1 F2025: R1.8 billion).

An impairment assessment was performed during the period. At 30 June 2023, an impairment charge amounting to R2.7 billion was recognised relating to the Eland mine. The estimation of recoverable value is most sensitive to commodity prices and the US dollar/South African Rand exchange rate (“Exchange Rate”). Accordingly, as a result of a significant increase in forecast long-term prices and the resultant impact on the recoverable amount for Eland, a reversal of the previously recognised impairment charge was warranted. In terms of International Financial Reporting Standards (“IFRS”) the amount of the reversal is limited to what the depreciated carrying value of the assets would have been as at 31 December 2025, had the assets not been impaired. As a result, an impairment reversal of R2.5 billion was recognised in the consolidated statement of profit or loss and other comprehensive income.

In accordance with IFRS the utilisation of a deferred tax asset is dependent on future taxable profits being in excess of the profits arising from the reversal of existing taxable temporary differences. As a result of the latest forecast commodity prices, a reassessment was performed regarding the utilisation of a deferred tax asset relating to Eland Platinum Proprietary Limited, and it is believed that it is probable that a deferred tax asset will be utilised in the near term. Accordingly, a deferred tax asset amounting to R706.0 million was recognised at the period end.

Metal inventory on hand increased to 527 395 4E oz, with a carrying value of R10.9 billion and a sales value of R25.4 billion when applying the 4E basket price and the Exchange Rate as at 31 December 2025.

Our operations generated cash to the value of R6.6 billion, before cash capital expenditure of R2.7 billion.

As at 31 December 2025, the group’s gross cash balance amounted to R9.3 billion, with net debt of R2.6 billion and a net debt to EBITDA ratio of 0.24.

At period end, Northam’s total available banking facilities amount to R12.3 billion, comprising a revolving credit facility (RCF) of R11.3 billion and a general banking facility (GBF) of R1.0 billion. Both these facilities remain undrawn.

Capital expenditure

Capital expenditure is attributable to significant activity on the Western extension project at Zondereinde, the ongoing ramp-up at Eland, and mining fleet purchases and concentrator upgrades at Booysendal South.

During the period, underground tunnel development within the Western extension progressed as planned, with over 2 000 metres of additional access tunnels having been advanced. Strike development has reached the fifth mining line, raises are being developed on the third mining line, and stoping is in progress on the first two mining lines.

Crew productivity is continuing to benefit from the combination of better mining conditions and focussed logistics over the ten mining levels, as well as the logistics decongestion resulting from the ongoing shift in UG2 stoping from the western to the eastern portions of the mine. Horizontal distance from the main shafts is, however, negatively impacting available face time for mining crews as well as the provision of services. Commissioning of the 3 shaft complex is envisaged to resolve these issues.

Equipping of 3 shaft, which has been designed for the conveyance of personnel and materials, together with services (including ventilation), process water, tailings slurry for backfill placement underground, as well as electricity, is progressing, and has reached a depth of 1 056 metres, with the establishment of the intermediate pumping chamber level having been completed. Reaming of 3a shaft, a dedicated, upcast ventilation way, to its final diameter of 4.8 metres, has reached 1 250 metres, with 111 metres remaining. Both shafts, together with their supporting surface infrastructure, are scheduled to be operational by April 2026. Development of the chairlift declines between levels 3 to 7 is complete, and equipping is scheduled in line with the shafts. Completion of the chairlift declines down to 12 level will continue in sequence.

Pilot drilling of 4 shaft, designed for rock hoisting, is complete, and reaming has now commenced. Ultimately, 4 shaft is envisaged to create optimal ore extraction conditions for the Western extension.

At Eland, the decline systems have been advanced 3 760 metres, which has accessed 11 strike drives. We require 11 strike drives for steady state production, but need to replenish depletion of strikes over time, therefore decline development will continue at an accelerated rate. The completion of a 4.5 metre diameter raise-bored ventilation shaft during the previous financial year significantly improved environmental conditions, particularly in the deeper sections of the mine that are critical to the medium-term ramp-up. It also allowed the mine’s ventilation circuit to be reconfigured, which is enabling improved decline development rates, further enhancing operational flexibility and de-risking the mine build programme.

Stoping of UG2 Reef is continuing, with 47 crews now deployed, averaging 9 600 square metres of stoping per month. Processing of run of mine ore sources is ongoing, together with third-party surface material. Enhancements to the processing circuits, together with improving feed grades, have led to improvements in both PGM and chrome recovery, with further upgrades and optimisation in progress. In addition, surplus capacity in the PGM and chrome circuits is allowing the treatment of UG2 ore from Zondereinde, where mining production currently exceeds concentrator capacity, delivering benefits to both operations.

Upgrades to the BMR plant at Northam’s metallurgical operations located at Zondereinde, to align capacity to that of the smelter circuit, are almost complete. Additional copper electrowinning cells were commissioned and upgrades to the second stage leaching circuits have been completed, as well as the construction of a second nickel sulphate crystalliser. In addition, vacuum pan dryers have been installed which reduce sulphur dioxide emissions in the BMR. We will continue to extract additional incremental improvements over the coming years.

The development of an 80 MW solar power facility at Zondereinde is in progress. Development is in collaboration with an Independent Power Producer (IPP) through a Power Purchase Agreement (PPA). Power will be supplied behind the Eskom meter and will thus not be exposed to load curtailment events. Construction is almost complete, and commissioning is scheduled during the second half of the current financial year. Once operational, the facility will improve security of power supply, whilst reducing energy costs and the operation’s carbon footprint.

In addition, we are developing self-build renewable energy projects at our mine sites, comprising solar plants supplemented with utility scale battery storage. Construction of the first of these projects, at Eland mine, comprising 20 MW solar, with 40 MWh of battery storage, will commence during the second half of the current financial year. Following this, a 250 MWh battery park will be installed at Zondereinde, supplementing the soon to be commissioned solar facility.

Capital expenditure for the remainder of the current financial year is estimated at R3.8 billion, with the bulk thereof to be invested in accelerated elective growth capital together with an aggressive renewable energy programme for the group.

Conclusion

Northam’s belief in the inherent value of the metals we produce, together with our long-held view of shrinking global primary production, have been the drivers behind our growth strategy. This strategy has required the investment of significant capital, both in the acquisition of quality assets, together with the development of those assets into world class mining and mineral processing operations. A significant pipeline of metal has also been funded and remains unencumbered.

Northam’s view is that primary supply will continue to decline unabated deep into the next decade due to the extended lead times for the development of new mines.

Northam’s operations are high-yielding quality assets with long operating lives, and our market share of primary PGM and chrome production is thus expected to grow over time.

We have funded our growth strategy through the very successful Zambezi empowerment transaction, internally generated cash flows and through our access to the debt market. This has enabled Northam to expand production without shareholder dilution. Northam will continue to allocate capital in this manner to ensure the sustainability of our operations well into the future, whilst returning value to shareholders.

The financial information contained in this announcement is the responsibility of the board of directors of Northam Holdings and has not been reviewed or reported on by Northam Holdings’ auditors, PricewaterhouseCoopers Incorporated. The reviewed results of Northam Holdings for H1 F2026 are expected to be published on or about Friday, 27 February 2026.

Johannesburg
9 February 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Disclosure of an acquisition of a beneficial interest in Northam Holdings securities

In accordance with section 122(3)(b) of the Companies Act, No. 71 of 2008, as amended (“Companies Act”), and paragraph 3.83(b) of the JSE Limited Listings Requirements (“JSE Listings Requirements”), Northam Holdings shareholders are advised that the company has received notification, in the prescribed form, from BlackRock, Inc. (“BlackRock”) advising that it has acquired a beneficial interest in the securities of Northam Holdings, such that BlackRock now holds a beneficial interest of 5.04% in the company’s total issued share capital.


In accordance with section 122(3)(b) of the Companies Act, No. 71 of 2008, as amended (“Companies Act”), and paragraph 3.83(b) of the JSE Limited Listings Requirements (“JSE Listings Requirements”), Northam Holdings shareholders are advised that the company has received notification, in the prescribed form, from BlackRock, Inc. (“BlackRock”) advising that it has acquired a beneficial interest in the securities of Northam Holdings, such that BlackRock now holds a beneficial interest of 5.04% in the company’s total issued share capital.

The company will file the relevant notification with the Takeover Regulation Panel and the Companies and Intellectual Property Commission, as required in terms of sections 122(3)(a) and 122(3A) of the Companies Act.

The board of directors of Northam Holdings (“Board”) accepts responsibility for the information contained in this announcement and certifies that, to the best of the Board’s knowledge and belief, the information contained in this announcement is true and that there are no facts that have been omitted which would make any statement in this announcement false or misleading and that this announcement contains all information required by law and the JSE Listings Requirements.

Johannesburg
29 January 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Disclosure of an acquisition of a beneficial interest in Northam Holdings securities

In accordance with section 122(3)(b) of the Companies Act, No. 71 of 2008, as amended (“Companies Act”), and paragraph 3.83(b) of the JSE Limited Listings Requirements (“JSE Listings Requirements”), Northam Holdings shareholders are advised that the company has received notification, in the prescribed form, from Fairtree Asset Management Proprietary Limited, on behalf of its clients (“Fairtree”), advising that it has acquired a beneficial interest in the securities of Northam Holdings, such that Fairtree now holds a beneficial interest of 5.03% in the company’s total issued share capital.


In accordance with section 122(3)(b) of the Companies Act, No. 71 of 2008, as amended (“Companies Act”), and paragraph 3.83(b) of the JSE Limited Listings Requirements (“JSE Listings Requirements”), Northam Holdings shareholders are advised that the company has received notification, in the prescribed form, from Fairtree Asset Management Proprietary Limited, on behalf of its clients (“Fairtree”), advising that it has acquired a beneficial interest in the securities of Northam Holdings, such that Fairtree now holds a beneficial interest of 5.03% in the company’s total issued share capital.

The company will file the relevant notification with the Takeover Regulation Panel and the Companies and Intellectual Property Commission, as required in terms of sections 122(3)(a) and 122(3A) of the Companies Act.

The board of directors of Northam Holdings (“Board”) accepts responsibility for the information contained in this announcement and certifies that, to the best of the Board’s knowledge and belief, the information contained in this announcement is true and that there are no facts that have been omitted which would make any statement in this announcement false or misleading and that this announcement contains all information required by law and the JSE Listings Requirements.

Johannesburg
20 January 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more

Voluntary production update

Northam reports an increase of 3.7% in total equivalent refined platinum group metals (“PGMs”) produced from own operations, and an increase of 14.8% in chrome concentrate production, for the 6-month period ended 31 December 2025 (“H1 F2026”), compared to the corresponding 6-month period ended 31 December 2024 (“H1 F2025”).


Northam reports an increase of 3.7% in total equivalent refined platinum group metals (“PGMs”) produced from own operations, and an increase of 14.8% in chrome concentrate production, for the 6-month period ended 31 December 2025 (“H1 F2026”), compared to the corresponding 6-month period ended 31 December 2024 (“H1 F2025”).

Key production metrics from own operations for H1 F2026 compared to H1 F2025 are as follows:

H1 F2026 H1 F2025
PGM production oz 4E oz 4E % variance
Equivalent refined metal production from own operations at Zondereinde 170 262 165 076 3.1
Concentrate production from own operations at Booysendal 261 148 256 759 1.7
Concentrate production from own operations at Eland 44 842 37 488 19.6
Total equivalent refined metal production from own operations 467 818 451 213 3.7
 
Chrome concentrate production tonnes tonnes % variance
Production at Zondereinde 241 454 242 402 (0.4)
Production at Booysendal 414 289 358 833 15.5
Production at Eland 167 016 115 387 44.7
Total production 822 759 716 622 14.8

Equivalent refined PGMs from third parties amounted to 83 448 oz 4E (H1 F2025: 59 743 oz 4E), representing an increase of 39.7%.

Our operations performed well. Zondereinde is benefitting from logistics decongestion as a result of the ongoing shift of UG2 stoping from the western to the higher-yielding eastern portions of the mine, as well as an increase in mining productivity arising from focussed Merensky stoping in the Western extension. Booysendal continues to focus on productivity and efficiency gains. Eland is making positive progress in its ramp-up programme with improvements achieved in both square metres and tonnes mined.

At Zondereinde, the ramp-up of stoping continues within the Western extension section. Equipping of 3 shaft for personnel and material transport, as well as the provision of services, is nearing completion. Reaming of 3a ventilation shaft also continues. Both shafts are scheduled for commissioning during the first quarter of the 2026 calendar year. This will deliver sustainable efficiency benefits to mining in the Western extension. Pilot drilling of 4 shaft, which will be a rock hoisting shaft, is complete, and reaming has commenced.

At Booysendal, decline development is continuing in order to increase mineable reserves and operational flexibility.

At Eland, ore production from underground mining is ramping up. In addition, the reconfiguration of the mine’s ventilation circuit has enabled multi-blast conditions, which allow accelerated decline development rates. Focus remains on strike and raise development in order to increase mineable reserves. The ongoing ramp-up of stoping is improving feed volumes and grades to the concentrator, and further enhancements to the concentrator circuits are yielding additional benefits to PGM and chrome production.

At the group’s metallurgical facilities, upgrades to the base metal removal plant have been completed and the new furnace slag concentrator is processing slag inventory at a satisfactory pace.

Johannesburg
14 January 2026

Corporate Advisor and Sponsor to Northam Holdings
One Capital

Corporate Advisor and Debt Sponsor to Northam Platinum
One Capital

Read more